Campanhã residents given June 2027 deadline to leave homes for high-speed rail

Topicshigh-speed railurban mobilityagricultural land abandonment

Residents of Campanhã, in Porto, whose homes lie on the route of the new Lisbon–Porto high-speed line must leave by the end of June 2027. The AVAN consortium expects to finish first contacts within two weeks. The works will affect 44 homes, seven businesses and three other buildings. A municipal housing development in Noêda is one rehousing option, though permanent homes could take one to two years, so some 25 to 30 households would need temporary accommodation. At a public meeting, residents complained that valuation reports were not being shared and that deadlines were unclear.

Summarised by Sustainable Living from Portugal Resident — Read the original ↗

Source published 25 November 2026